Happy New Year To All!!!
Our gift today was having the granite counter tops installed this morning.
Next is light fixtures, plugs, outlets and interior doors.
Tuesday, December 31, 2013
Saturday, December 21, 2013
December 21 - Update
Our plumber/HVAC fella was on site most of the week. We have a working furnace and running water AND toilets!!!! How very exciting this is.
The siding was all finished up this week as well.
The floors were laid this week and they are very nice. We did have issues with the installers marking up the walls in every room, really wished they had been more careful. They either scratched, left black marks or gouged them. We have met with our supplier who hired them. He was shocked by the amount of damage and he will have the walls fixed. I gave him the name of our dry wall mudder & painter to hire them. Hopefully this gets fixed up early January.
Above & below - two front bedrooms
Main bathroom...with toilet, sink and taps!! :)
Above is Master bedroom.
Below - ensuite bathroom looking into bedroom.
What do you think of this? (Feel free to post a comment anytime). We think it's beautiful!! The house is really coming together. Counter top is penciled in for installation on January 6, 2014! Now that the floor has been laid, the cabinet installer will be back to put the kick plates at the bottom of the cupboards & permanently place the island.
Sunday, December 15, 2013
December 15 - View from Apartment
As apartments go, we are pretty lucky. Especially with our view. We are in the back building of the complex overlooking the green space along the Seine River. This is the one and same river that flows behind the house in Lorette!
Our view is spectacular and we love to watch the deer come out of the bush to graze and visit.
Our view is spectacular and we love to watch the deer come out of the bush to graze and visit.
View from our balcony.
Our daily visitors...yesterday there were 7!!!
December 15 - Update
Chug-chug-chug...things are still moving along.
The cold put a stop to the siding installation last week (-30 C as I type this) but tomorrow it's suppose to warm up to around -10 C so they said that they would be back to finish it up. :]
Plumber/HVAC fella has been onsite since Wednesday and is making great headway. We should have a toilet by the end of the week. (It's the small things in life that get us so excited!!)
Alanna & her Journeyman will be on site starting Tuesday to hook up the well pump, septic field, HRV, HWT & furnace. The majority of the light fixtures are on site so Alanna will start to install these as well. Once we get the outlets & switches she will do that too.
The wood stove will be installed in the new year. Almost had it in before Christmas but I forgot to order the tile/concrete board heat pad that goes underneath, so we did that on Thursday. My bad.
They started installing the floor on Wednesday and should be done by Tuesday this week. The 3 bedrooms & WIC are completed & they have laid the tile in the ensuite & main bathrooms (they still have to do the grout).
The cold put a stop to the siding installation last week (-30 C as I type this) but tomorrow it's suppose to warm up to around -10 C so they said that they would be back to finish it up. :]
Plumber/HVAC fella has been onsite since Wednesday and is making great headway. We should have a toilet by the end of the week. (It's the small things in life that get us so excited!!)
Alanna & her Journeyman will be on site starting Tuesday to hook up the well pump, septic field, HRV, HWT & furnace. The majority of the light fixtures are on site so Alanna will start to install these as well. Once we get the outlets & switches she will do that too.
The wood stove will be installed in the new year. Almost had it in before Christmas but I forgot to order the tile/concrete board heat pad that goes underneath, so we did that on Thursday. My bad.
They started installing the floor on Wednesday and should be done by Tuesday this week. The 3 bedrooms & WIC are completed & they have laid the tile in the ensuite & main bathrooms (they still have to do the grout).
Guest room
Walk in closet
Main bathroom
And for those of you who are wondering how Alanna's pup is doing...he's getting big and is such a sweetheart. He is so laid back, loves to cuddle and thinks that he still fits in a lap.
Cuda - 16 weeks
Sunday, December 8, 2013
December 8 - Exterior Almost Complete
Siding is almost complete. Downspouts and eaves troughs are up. The downspouts are the same colour as the siding so they disappear. The windows doors have a 3" trim and in the spring we will be installing the shutters on the front windows to finish off the look.
December 8 - Cabinets Installed & Flooring Onsite
All of the cabinets were installed last week. They are coming Thursday afternoon to template for the granite counter tops & I'm hoping that they will be installed before Christmas.
As you can tell, I prefer drawers to cupboards.
Space between cabinets is for the dishwasher
Main Bathroom
Ensuite
2 piece bathroom off mudroom
On the left, tile for front entrance/mudroom. Piles of boxes are engineered hardwood for everywhere else. Should be installed this coming week. Will confirm tomorrow.
Monday, December 2, 2013
December 2 - Interior Update
The inside of the house has been painted & we are very happy with the job they did. Our designer suggested that we keep the colours neutral until we get a feel for the house and see what the natural light is like once we have the furniture in.
One more coat of drywall mud and we can paint this little wall in the laundry room.
Guest room
Office/den
Master Bedroom
Thank you to Susan & Glenn who came out tonight to help me prep for cabinets to be installed. We vacuumed once again and then washed the floors where the cabinets are going at the end of the week. Washed up the kitchen & 3 bathrooms a few times...til we ran out of water. lol
Subscribe to:
Posts (Atom)