Sunday, January 13, 2013

January 13 - Update

Again, no visible changes, but things are happening.

  • The trench for the Hydro wires is all filled in.
  • The new basement windows are on order. The concrete guy took full responsibility for his error and is paying for 3 new windows that will still meet the egress code. Hopefully these are received and installed by the end of January (fingers crossed).
  • The framework for the 3 pocket doors is done.
  • We've been doing a fair bit of research/planning: appliances; bathroom vanities; kitchens; etc.
Marshall is out there today planning on starting the soffit & fascia and a few other tasks.

I know we did not get the blizzard that our friends in Newfoundland did, but it was still very crazy here on Friday. Have a look at these pictures that Marshall took today. Once we get the soffit and fascia up, it will keep the snow out. We are just happy that we have windows, we would have needed a snow blower to clear the snow!! Marshall went out on Thursday to cover up the basement windows to keep snow out in case we got the blizzard that they were forecasting...very happy he did! Can't imagine how it looked out there on Friday night when the wind was howling.

Snow sitting on the rafters.

 Hallway is shoveled...looking into one of the front bedrooms.

In hallway by the bedrooms looking into the dining room.

The compressor & saw even got snowed on.