Wednesday, January 29, 2014

January 29 - Move In Delayed

We met with the building inspector at the house today to make sure that we are on the right track and in all that has been going on a little detail was missed on our part. 
Before we can get an occupancy permit, the bay in the garage that will be the shop has to be built to fire code as it is attached to the house. The stars must have aligned for us because Henri (our main house builder from the beginning) is available to do the work!!!
So we will get all the materials and Henri will get started on this Friday afternoon.
As well (for adherence to code) the basement has to be dry walled to cover up the styrofoam Logix foundation. Before we can drywall we have to do the electrical. Bob, the inspector, said that this has to be complete within 30 days after moving in, but we would like it done before we move in.
So it looks like we will not be giving notice to move out of our apartment at the end of February, more like the end of March. But as soon as the house passes final inspection we will move in...even if it's March 3!!
So this weekend we will work on tidying the garage and few interior things as well.